Complete the following Master Schedule record (current week: week 5). Note: DO NOT type your calculation procedure. You only need to type the correct numbers. Week 5 6 7. 8 Forecasted demand 500 450 500 350 Booked Orders 400 600 500 450 MPS (Planned Prod.) 700 800 o Projected 150 Ending Inv. (actual) -250 No Available to Promise No ATP ATP