Question: Complete the following task using Critical Path Method Project Scheduler. [13 Marks] A building for an electronics product factory is to be built. The construction
Complete the following task using Critical Path Method Project Scheduler. [13 Marks]
A building for an electronics product factory is to be built. The construction will be done in a step wise fashion according to the required following activities. Some of these activities must be completed before other activities can be started.
| Activity | Predecessor | Duration (Days) | Total Float |
| A | -- | 28 |
|
| B | C | 40 |
|
| C | A | 30 |
|
| D | B | 16 |
|
| E | C | 4 |
|
| F | D and E | 20 |
|
| G | F | 8 |
|
| H | G | 36 |
|
| I | F | 8 |
|
| J | H | 12 |
|
- Implement a network activity (diagram) in the Critical Path Method Project Scheduler to create the activity network to identify critical path. (Save the file and submit it on Moodle).
(06 Marks)
- Write the letters that represent critical path here: __________________________ (01 Marks)
Write the total float for all the activities which you must write in the empty column from the data given in the software interface.