Question: Complete the MRP record given below. If an L4Llot-sizing rule is used, what is the planned order release for week 3? Item: ABC Order policy:

Complete the MRP record given below. If an
Complete the MRP record given below. If an L4Llot-sizing rule is used, what is the planned order release for week 3? Item: ABC Order policy: Lead time: 2 weeks Quantity on hand: 20 Week 1 2 3 4 5 6 7 00 65 15 Gross requirements 45 40 80 60 25 10 Scheduled receipts 150 Projected on-hand Inventory Planned receipts Planned order releases Greater than 20 but less than or equal to 40 Greater than 60 but less than or equal to 80