Question: Complete the network analysis for the data given above. Produce the resulting Gantt chart. Identify the critical path. If the execution of Task G was

Complete the network analysis for the data given above.
Produce the resulting Gantt chart.
Identify the critical path.
If the execution of Task G was delayed by five (5) due to an Employer risk (e.g. late possession of
a part of the site) in the circumstances is the Contractor entitled to an extension of time (EOT) to
complete the project and if so how many days EOT? Please explain your answer.
Task H is delayed by three (3) days due to an Employer risk (e.g. late possession of a part of the
site) is the Contractor entitled to an extension of time (EOT) to complete the project and if so
how many days EOT? Please explain your answer.
What difference, if any, would knowledge of a concurrent delay of seven (8) days in completing
Task C because of a contractor HR problem have to you answer at 5 above? Please explain your
answer
The HR issue deteriorates, and Task C is delayed by a further eight (8) days what impact, if any,
would this have on the contractor's entitlement to an extension of time for the delay to Task G
referred to at point 4 above? Please explain your answer.
Complete a revised network analysis taking account of the cumulative effect of each of the
delays set out in points 4 to 7 above.
 Complete the network analysis for the data given above. Produce the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!