Question: COMPLETE THE NETWORK DIAGRAM a . How long the total process will take. b . Which jobs can be delayed without delaying the early start
COMPLETE THE NETWORK DIAGRAM
a How long the total process will take.
b Which jobs can be delayed without delaying the early start of any subsequent activity?
Activity Job and Description Immediate predecessors Time Hours
A Start
B Get computer printouts of customer purchases A
C Get stock records for the month A
D Reconcile purchase printouts and stock records B C
E Total stock records by department B C
F Determine reorder quantities for coming period E
G Prepare stock reports for purchasing agents D F
H Finish G
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock