Question: COMPLETE THE NETWORK DIAGRAM a . How long the total process will take. b . Which jobs can be delayed without delaying the early start

COMPLETE THE NETWORK DIAGRAM
a. How long the total process will take.
b. Which jobs can be delayed without delaying the early start of any subsequent activity?
Activity Job and Description Immediate predecessors Time (Hours)
A Start -0
B Get computer printouts of customer purchases A 13
C Get stock records for the month A 24
D Reconcile purchase printouts and stock records B, C 35
E Total stock records by department B, C 23
F Determine reorder quantities for coming period E 41
G Prepare stock reports for purchasing agents D, F 22
H Finish G 0