Question: Complete the statement. Using the PERT estimation formula, optimistic time is __________. The typical time required to complete a task The longest possible time required
Complete the statement. Using the PERT estimation formula, optimistic time is __________. The typical time required to complete a task The longest possible time required to complete a task The shortest possible time required to complete a task The expected time required to complete a task