Question: complexity weight table, estimate the total function point count. Assume historical data suggest five function points equal one person a month and six people have



complexity weight table, estimate the total function point count. Assume historical data suggest five function points equal one person a month and six people have been assigned to work on the project. TABLE 5.2 Simplified Basic Function Point Count Process for a Prospective Project or Deliverable a. What is the estimated project duration? b. If 20 people are available for the project, what is the estimated project duration? c. If the project must be completed in six months, how many people will be needed for the project