Question: Component C is being ordered from a supplier. You have a planned order receipt for 4 , 7 5 0 units of Component C in

Component C is being ordered from a supplier. You have a planned order receipt for 4,750 units of Component C in Week 11. If, on average, your supplier provides you with orders that contain 12 units of scrap, what would be the Planned Order Release quantity for this item?
Round up to a full item. ANSWER: 5,398