Question: Compress the project timelines in this problem using the least cost method one unit at a time. Reduce the schedule until you reach the crash
Compress the project timelines in this problem using the least cost method one unit at a time. Reduce the schedule until you reach the crash point (shortest duration possible) of the network. For each duration reduction, identify what activity(s) was crashed and the new adjusted total cost.
| Activity Crash | Cost (slope) | Maximum Crash Time | Normal Time | Normal Cost |
| B | 100 | 2 | 3 | 150 |
| C | 50 | 1 | 4 | 200 |
| D | 60 | 1 | 3 | 200 |
| E | 70 | 2 | 4 | 200 |
| F | 90 | 1 | 3 | 150 |