Question: Compute expected time for each activity, also variance. Activity o ( optimistic ) p ( pessimistic ) m ( most likely ) Immediate Predecessor te

Compute expected time for each activity, also variance.
Activity
o (optimistic)
p (pessimistic)
m (most likely)
Immediate Predecessor
te (estimated time)
Variance
A
4
6
5
5.0
0.1
B
2
8
5
5.0
1.0
C
5
9
7
A
7.0
0.4
D
4
6
5
A
5.0
0.1
E
2
6
4
B
4.0
0.4
F
3
9
6
B
6.0
1.0
G
10
12
11
C, E
11.0
0.1
H
7
9
8
D,F
8.0
0.1 Determine the probability the project will NOT be finished in 26 days or less?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!