Question: compute fixed and variable overhead variances given the following information. show work actual number units produced 10000 budgeted number units 900 standard:variable overhead $1.05 per
compute fixed and variable overhead variances given the following information. show work
actual number units produced 10000
budgeted number units 900
standard:variable overhead $1.05 per unit
standard:fixed overhead $211,500
actual variable factory overhead $10,000
actual total factory overhead $215,500