Question: Compute the activity variance for the cost where: Planned activity of 610 units. Actual units 613. Cost formula is $1,700 per month plus $8 per
Compute the activity variance for the cost where: Planned activity of 610 units. Actual units 613. Cost formula is $1,700 per month plus $8 per unit. Actual cost was $6,870. $24 F $24 U O $290 F $290 U