Compute the Advance Billing assuming the following information: total bid $60,000; total estimated cost of construction $50,000;
Fantastic news! We've Found the answer you've been seeking!
Question:
Compute the Advance Billing assuming the following information: total bid $60,000; total estimated cost of construction $50,000; amount spent to date $5,000. What is the amount to be billed using percentage of completion? 5000 6000 10000 60000
Related Book For
Accounting Principles Part 3
ISBN: 978-1118306802
6th Canadian edition Volume 1
Authors: Jerry J. Weygandt, Donald E. Kieso, Paul D. Kimmel, Barbara Trenholm, Valerie Kinnear, Joan E. Barlow
Posted Date: