Question: Compute the DIRECT LABOR (DL) USAGE VARIANCE, the DLRATE VARIANCE, and the TOTAL DL COST VARIANCE for the assembly technicians. ASSEMBLY TECHNICIANS Direct Labor (DL)
Compute the DIRECT LABOR (DL) USAGE VARIANCE, the DLRATE VARIANCE, and the TOTAL DL COST VARIANCE for the assembly technicians.
ASSEMBLY TECHNICIANS
Direct Labor (DL) Usage Variance: (STD DL Hours Quantity Actual DL Hours Quantity) x Std Hourly Rate
(13,505-3064) x 18 = 187,938 U
DIRECT LABOR (DL) RATE VARIANCE: (STD DL Hrly Rate Actual DL Hrly Rate) x Actual DL Hours Quantity
(18.65-18.00) x 3064 = 1,991.60 F
TOTAL DIRECT LABOR (DL) COST VARIANCE: DL Usage Variance + DL Rate Variance
187,938 1991.60 = 185,946.40
What does this subset of variance analysis tell you about the PERFORMANCE of various managers?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts