Question: Compute the discounted payback period (DPB) for a project with the following cash flows, if the companys discount rate is 12%. Initial outlay = -$500
Compute the discounted payback period (DPB) for a project with the following cash flows, if the companys discount rate is 12%.
Initial outlay = -$500
Cash flows: Year 1 = $375
Year 2 = $98
Year 3 = $362
Year 4 = $35
Please round your answer to the second decimal. E.g. 1.23