Question: Compute the discounted payback period (DPB) for a project with the following cash flows, if the companys discount rate is 12%. Initial outlay = -$500

Compute the discounted payback period (DPB) for a project with the following cash flows, if the companys discount rate is 12%.

Initial outlay = -$500

Cash flows: Year 1 = $375

Year 2 = $98

Year 3 = $362

Year 4 = $35

Please round your answer to the second decimal. E.g. 1.23