Question: Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.)
| Project C | ||||||
| Time: | 0 | 1 | 2 | 3 | 4 | 5 |
| Cash flow | $1,300 | $600 | $570 | $610 | $360 | $160 |
| Discounted payback period | years |
| Should the project be accepted or rejected? | ||||
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts