Question: Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer
| Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) |
| Project E | ||||||
| Time: | 0 | 1 | 2 | 3 | 4 | 5 |
| Cash flow | $2,700 | $830 | $840 | $760 | $540 | $340 |
IRR % ____________
| Should the project be accepted or rejected? _________ |