Question: Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer
| Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) |
| Project E | ||||||
| Time: | 0 | 1 | 2 | 3 | 4 | 5 |
| Cash flow | $2,000 | $750 | $780 | $720 | $500 | $300 |
| IRR | % |
| Should the project be accepted or rejected? | ||||
|