Question: Compute the IRR statistic for Project E. The appropriate cost of capital is 7 percent. Note: Do not round intermediate calculations and round your final
Compute the IRR statistic for Project E. The appropriate cost of capital is 7 percent.
Note: Do not round intermediate calculations and round your final answer to 2 decimal places.
Project E
| Time: | 0 | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|---|
| Cash flow: | $3,600 | $1,110 | $1,050 | $900 | $680 | $480 |
IRR _____%?
Should the project be accepted or rejected?
(Click to select) Rejected Accepted