Question: Compute the IRR statistic for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer
Compute the IRR statistic for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: Cash flow -$1,900 1 $710 2 $750 3 $700 4 $480 5 $280 IRR 18.96 % Should the project be accepted or rejected? accepted rejected