Question: Compute the Labor Variance with work shown from the table below Actual Material used: 30,000 Actual Cost: $7.75/Unit Actual Labor Hrs: 33,000 Actual Labor Rate:

Compute the Labor Variance with work shown from the table below

Actual Material used: 30,000 Actual Cost: $7.75/Unit Actual Labor Hrs: 33,000 Actual Labor Rate: $15/Hr:

Budgeted production (units) 16,600 20,600 22,800 60,000
Labor requirements per unit (hours) 0.5 0.5 0.5 0.5
Total labor hours needed 8,300 10,300 11,400 30,000
Labor rate (per hour) $16 $16 $16 $16
Labor dollars $132,800 $164,800 $182,400 $480,000