Question: Compute the Labor Variance with work shown from the table below Actual Material used: 30,000 Actual Cost: $7.75/Unit Actual Labor Hrs: 33,000 Actual Labor Rate:
Compute the Labor Variance with work shown from the table below
Actual Material used: 30,000 Actual Cost: $7.75/Unit Actual Labor Hrs: 33,000 Actual Labor Rate: $15/Hr:
| Budgeted production (units) | 16,600 | 20,600 | 22,800 | 60,000 | ||||
| Labor requirements per unit (hours) | 0.5 | 0.5 | 0.5 | 0.5 | ||||
| Total labor hours needed | 8,300 | 10,300 | 11,400 | 30,000 | ||||
| Labor rate (per hour) | $16 | $16 | $16 | $16 | ||||
| Labor dollars | $132,800 | $164,800 | $182,400 | $480,000 | ||||