Question: Compute the multifactor productivity measure for an eight-hour day in which the usable output was 300 units, produced by four workers who used 500 pounds

Compute the multifactor productivity measure for
Compute the multifactor productivity measure for an eight-hour day in which the usable output was 300 units, produced by four workers who used 500 pounds of materials. Workers have an hourly wage of $20, and material cost is $1 per pound. Overhead is 1.6 times labor cost. a 1.57 units of output per dollar of input d. 1.38 units of output per dollar of mput b 1.27 units of output per dollar of input e. None of the choices c. 1.48 units of output per dollar of input