Question: Compute the NPV for Project M if the appropriate cost of capital is 9.15 percent. (Do not round intermediate calculations and round your final answer

Compute the NPV for Project M if the appropriate cost of capital is 9.15 percent. (Do not round intermediate calculations and round your final answer to 2 decimal place.)

Project M

Time: 0

12345

Cash flow $1,000

$350 $480 $520 $600 $100

NPV

$

Should the project be accepted or rejected?

Accepted / Rejected