Question: Compute the NPV for Project M if the appropriate cost of capital is 9.15 percent. (Do not round intermediate calculations and round your final answer
Compute the NPV for Project M if the appropriate cost of capital is 9.15 percent. (Do not round intermediate calculations and round your final answer to 2 decimal place.)
Project M
Time: 0
12345
Cash flow $1,000
$350 $480 $520 $600 $100
NPV
$
Should the project be accepted or rejected?
Accepted / Rejected