Question: Compute the NPV statistic for Project K if the appropriate cost of capital is 7 percent. Note: Negative amount should be indicated by a minus
Compute the NPV statistic for Project K if the appropriate cost of capital is 7 percent.
Note: Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.
Project K
| Time: | 0 | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|---|
| Cash flow: | $11,000 | $5,500 | $6,500 | $6,500 | $5,500 | $11,000 |