Question: Compute the NPV statistic for Project Y given the following cash flows if the appropriate cost of capital is 10 percent. Project Y Time 0
Compute the NPV statistic for Project Y given the following cash flows if the appropriate cost of capital is 10 percent.
Project Y
| Time | 0 | 1 | 2 | 3 | 4 | 5 |
| Cashflow | $50,000 | $7,000 | $20,000 | $20,000 | $20,000 | $10,000 |
Multiple Choice:
A. -$19,594.29
B. $107,788.34
C. $7,788.34
D. $9,367.11
Thanks!!