Question: Compute the NPV statistic for Project Y if the appropriate cost of capital is 10 percent.(Negative amount should be indicated by a minus sign.Do not
| Compute the NPV statistic for Project Y if the appropriate cost of capital is 10 percent.(Negative amount should be indicated by a minus sign.Do not round intermediate calculations and round your finalanswer to 2 decimal place.) |
| Project Y | |||||
| Time: | 0 | 1 | 2 | 3 | 4 |
| Cash flow | $8,500 | $3,730 | $4,560 | $1,900 | $680 |
| NPV | $ |
| Should the project be accepted or rejected? | ||
|