Question: Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent and the maximum ailowable payback period Is three years.
Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent and the maximum ailowable payback period Is three years. (If the project never pays back, then enter a "0" (zero).) Projects Time: 2 -3 4 Cashflow: -$11,300 $3,380 $4,240 $1,588 50 $1,060 Payback year Should the project be accepted or rejected? accepted rejected