Question: Compute the payback statistic for Project Y and recommend whether the firm should accept or reject the project with the cash flows shown as follows
Compute the payback statistic for Project Y and recommend whether the firm should accept or reject the project with the cash flows shown as follows it the appropriate cost of capitalis 12 percent and the maximum allowable payback is three years 4 Time: Cash flow 0 -250 1 50 2 100 3 200 5 200 200 225 years, accept 233 years, reject 250 years accept 2 50 years.reject 2.5 pts Question 37 A project costs 5101.000 today and is expected to generate cash flows of $21,000 per year for the next 10 years. Estimate the IRR of the project 1138 percent O 1247 percent 1613 percent 19.32 percent