Question: Compute the PI statistic for Project Q if the appropriate cost of capital is 12 percent. (Do not round intermediate calculations. Round your final answer
Compute the PI statistic for Project Q if the appropriate cost of capital is 12 percent. (Do not round intermediate calculations. Round your final answer to 2 decimal places.)
| Project Q | |||||||
| Time: | 0 | 1 | 2 | 3 | 4 | ||
| Cash flow | $12,200 | $3,950 | $4,780 | $2,120 | $2,750 | ||
| |||||||
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts