Question: Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 6 percent. Time: 0 1 2 3 4 5 Cash flow: 79 79 0 104 79 54