Question: Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown as follows
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 10 percent. Time: 0 1 2 3 4 5
Cash flow: 75 75 0 100 75 50
A - 2, accept
B - 1.1896, accept
C - 0.1896, reject
D - 10.1896, accept