Question: Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if

Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent.

Time: 0 1 2 3 4 5
Cash flow: -75 -75 0 110 85 60

rev: 05_08_2019_QC_CS-167988

Multiple Choice

  • 34.77, accept

  • 1.46, accept

  • 10.00, reject

  • 60.50, accept