Question: Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 9 percent.
| Time: | 0 | 1 | 2 | 3 | 4 | 5 |
| Cash flow: | -76 | -76 | 0 | 101 | 76 | 51 |
| 19.25%, accept | |
| 9.00%, reject | |
| 42.86%, accept | |
| 25.33%, accept |