Question: Compute the Pl statistic for Project Q if the appropriate cost of capital is 11 percent. (Do not round intermediate calculations and round your final
Compute the Pl statistic for Project Q if the appropriate cost of capital is 11 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Q Time: Cash flow 0 1 2 3 4 -$11,400 $3,550 $4,380 $1,720 $2,350 PI Should the project be accepted or rejected? accepted O rejected