Question: Compute the takt time for a system where the total time per shift is 370 minutes, there is one shift, and workers are given 311minute

Compute the takt time for a system where the total time per shift is 370 minutes, there is one shift, and workers are given 311minute breaks and 35 minutes for lunch. Daily demand is 342 units. (Round your answer to 2 decimal places.) What cycle time would match capacity and demand if demand is 176 units a day, there are 1 shift(s) of 461 minutes each, and workers are given three 30 minute breaks during each shift, one of which is for lunch or dinner? (Round your answer to 2 decimal places.)