Question: Compute the total direct cost for each project duration. If the indirect costs for each project duration are $450 (22 time units), $400 (21 time
Compute the total direct cost for each project duration. If the indirect costs for each project duration are $450 (22 time units), $400 (21 time units), $350 (20 time units), $300 (19 time units), $250 (18 time units), and $200 (17 time units), compute the total project cost for each duration. Then answer the questions.

| Activity | Predecessor | Crash Cost (Slope) | Maximum Crash Time | Normal Time | Normal Cost |
|---|---|---|---|---|---|
| A | None | 30 | 1 | 5 | 40 |
| B | A | 60 | 2 | 6 | 50 |
| C | A | 50 | 1 | 4 | 80 |
| D | A | 0 | 0 | 12 | 50 |
| E | B | 70 | 2 | 7 | 100 |
| F | C | 120 | 4 | 8 | 100 |
| G | D, E, F | 90 | 1 | 3 | 40 |
After crashing, the optimum cost for this project is $ 840 850 860 830