Question: Compute the variable-cost and fixed cost components using the high-low method Month January February March April Compute the variable-cost and fixed cost components using the

Month January February March April Compute the variable-cost and fixed cost components

Compute the variable-cost and fixed cost components using the high-low method

Month January February March April Compute the variable-cost and fixed cost components using the high-low method. r, Dress AL T + Fl Lassie Inc. accumulates the following data concerning a mixed cost, using miles as the activity level. Miles Driven 7,500 8,200 8,500 8,300 Total Cost $20,000 $21,100 $22,000 21 ,750