Question: Compute turnaround time with preemptive priority scheduling. Also compute the average turnaround time. Show the Gantt chart and other details. Process CPU Burst time Arrival
Compute turnaround time with preemptive priority scheduling. Also compute the average turnaround time. Show the Gantt chart and other details.
| Process | CPU Burst time | Arrival time | Priority |
| P1 | 25 | 5 | 5 |
| P2 | 10 | 10 | 3 |
| P3 | 15 | 15 | 4 |
| P4 | 20 | 20 | 2 |
| P5 | 30 | 25 |