Question: Computer Applications for Project ManagementAssignment Restricted Available from 2 0 January 2 0 2 4 , 1 2 : 0 0 PM Q . 2

Computer Applications for Project ManagementAssignment
Restricted Available from 20 January 2024,12:00 PM
Q.2 Based on the provided table, develop activities, determine their start and end points, identify preceding activities, and assign durations in weeks. (Upload File to auppm.com)
Activity
Preceding Activity
Estimate Weeks
Start
0
C
Start
3
D
C
6
A
C
8
E
D
4
B
A, E
5
F
E
3
End
B, F
0