Question: Computer chips: standard 3 chips /computer at $6.50. Chips used 130 to make 40 computers. What is the materials quantity variance? $65 favorable $845 favorable
Computer chips: standard 3 chips /computer at \$6.50. Chips used 130 to make 40 computers. What is the materials quantity variance? $65 favorable $845 favorable $65 unfavorable $845 unfavorable
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts