Computer Nerds, Inc., is planning a project to develop a commercial software package for PCs. They have come up with the following list of activities, times and precedence relationships.

Symbol Activity Description Predecessors (weeks) P Perform market survey 3 D Design graphic icons P 4 F Develop flow chart P 2 S Design input/output screens D, F 6 U Code Module 1 F 5 V Code Module 2 F 3 W Code Module 3 U 7 X Code Module 4 U, V 5 T Merge modules & Test program S, W, X 8 (i) Construct a Network diagram for this project. (ii) Identify all paths in the Network and the Critical Path. What is the Project completion time? (iii) What is the Slack of each path? (

Computer Nerds, Inc., is planning a project to
3 5. Computer Nerds, Inc., is planning a project to develop a commercial software package for PC's. They have come up with the following list of activities, times and precedence relationships. Immediate Activity Time Symbol Activity Description Predecessors (weeks) Perform market survey D Design graphic icons P 4 F Develop flow chart P 2 S Design input/output screens DF 6 U Code Module 1 F 5 V Code Module 2 F W Code Module 3 U 7 X Code Module 4 U. V 5 . Merge modules & Test program S.W.X 8 (i) Construct a Network diagram for this project. (ii) Identify all paths in the Network and the Critical Path. What is the Project completion time? (iii) What is the Slack of each path

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!