Question: Computer the capacity ( bottleneck rate ) in parts per hour of the following: ( 1 ) A balanced line with single - machine stations,

Computer the capacity (bottleneck rate) in parts per hour of the following:
(1) A balanced line with single-machine stations, all with average processing times of 15
minutes.
(2) A four-station line with single-machine stations, where the average processing times are 15,
20,10,12 minutes, respectively for stations 1,2,3 and 4.
(3) A four-station line with multimachine stations, where the number of (parallel) machines at
stations 1,2,3,4 is 2,6,10,3, respectively. The average processing times at stations are 10,
24,40,18 minutes, respectively.
(4) A three-station with ample equipment (i.e., such that operators are never prevented from
processing a job by a lack of equipment) staffed by 6 operators who are identical with
regard to average processing time and require 10,15 and 5 minutes, respectively on stations
1,2 and 3.(5) The same line as in the above case except that station 2 consists of only 2 parallel machines.
All other stations still have ample capacity.
until completion of the job? (use memoryless property)
(b) A part is currently been processed on that machine for 30 mins. What is the expected time
until completion of the job?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!