Question: Computers are assembled in a process with two resources. The first resource has a capacity of 5 computers per hour. The capacity of the second
Computers are assembled in a process with two resources. The first resource has a capacity of 5 computers per hour. The capacity of the second resource is 6.2 computers per hour. The first resource has 3 workers and the second resource has 1 worker. Demand for this process is 5.9 computers per hour. Wages are $12 per hour. What is the cost of direct labor(in $s)? per unit