Question: Concerning dispatching rules, which of the following is correct? Question 6 options: SPT is good at meeting due dates. CR is good at efficiency and
Concerning dispatching rules, which of the following is correct? Question 6 options: SPT is good at meeting due dates. CR is good at efficiency and high throughput. SPT is good at moving small jobs quickly through the process. All of these choices are correct. None of the above