Question: Concurrent activities are: Select one: a . Activities that use labor from the same group of workers. b . Activities that must be done one

Concurrent activities are:
Select one:
a.
Activities that use labor from the same group of workers.
b.
Activities that must be done one after the other.
c.
Activities that can be performed at the same time.
d.
Activities that use resources from the same resource pool.