Question: Conrad Construction Corp. has a $20 million contract to construct a building. The company estimates a gross profit of $4 million. During the current year,

 Conrad Construction Corp. has a $20 million contract to construct a

Conrad Construction Corp. has a $20 million contract to construct a building. The company estimates a gross profit of $4 million. During the current year, the company incurred $2 million of costs on the contract. Under the percentage-of-completion method, how much will Conrad Construction Corp. report as revenue in the current year? O $2,000,000 0 $10,000,000 0 $4,000,000 0 $2,500,000