Question: Consider 2 processes with their arrival time, burst time, deadline given below Develop Gantt chart of these processes employing EDF - Non-Preemptive scheduling. Process Arrival

Consider 2 processes with their arrival time, burst time, deadline given below Develop Gantt chart of these processes employing EDF - Non-Preemptive scheduling. Process Arrival Burst Time Deadline Pi P, 4