Question: Consider 4 jobs, A , B , C , D . The processing time of the 4 jobs are listed in the table below The
Consider jobs, A B C D The processing time of the jobs are listed in the table below
The jobs have different urgency levels. The relative urgencies are as below:
Job C is the least urgent. Job A and D are twice as urgent as C Job B is three times as urgent as C
Job
A
B
C
D
Processing Time
mins
mins
mins
mins
Which option correctly ranks the priorities of the jobs using the WSPT rule?