Question: Consider a 4-step worked-paced serial process with the following information: Steps 1 through 4 take 5, 15, 10, and 3 minutes per customer, respectively. There
Consider a 4-step worked-paced serial process with the following information: Steps 1 through 4 take 5, 15, 10, and 3 minutes per customer, respectively. There are 1, 5, 3, and 1 workers serving customers in steps 1 through 4, respectively. How many minutes does it take to serve 15 customers?
33
495
100
103