Question: Consider a capital budgeting example with 5 projects to select from. Let x i = 1 if project i is selected, 0 if not, 1
Consider a capital budgeting example with 5 projects to select from. Let xi = 1 if project i is selected, 0 if not, 1 i 5. Write the appropriate constraint. Conditions are independent.
No more than two of the projects can be chosen
| x1 + x2 + x3 2 | ||
| x1 + x2 + x3 > 1 | ||
| x1 + x2 + x3 + x4 + x5 2 | ||
| x1 + x2 + x3 + x4 + x5 > 1 |